()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
您可能感興趣的試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
A.project scope statement
B.project requirement
C.project charter
D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
最新試題
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
空白(3)處填()
空白(1)處填()
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
空白(2)處填()
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
空白(1)處填()
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
空白(5)處填()