Contract closeout is a process that involves()
A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix
You are working on the cost budget for one project. Which of the following is true()
A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.
A.Total float for the activity is 9 days.
B.The early finish date ofthe activity is the end ofthe day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
A.Benefitcontribution
B.Expertjudgment
C.Scoringmodels
D.Flowcharting
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
A.independentresource
B.individualworkload
C.workmilestone
D.workpackage
最新試題
An example of scope verification is ().
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
空白(3)處填()
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.
空白(1)處填()
The connection between two networks from an intemet is handled by a machine known as a()
空白(1)處填()
空白(2)處填()
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()