單項(xiàng)選擇題

Companycom is considering a large partitioned p5 590 to consolidate several smaller systems in their data center. Due to the complexity of the consolidation, the customer is asking the technical support specialist to give them a report which shows pre order PCI adapter placement and validates them against IBM's recommendations. The concern is that the factory will not install the adapters in the appropriate slots as the customer pre-selected.
What IBM tool is available to provide this?()

A.LPAR Validation Tool (LVT)
B.Personal Systems Configurator (PSC)
C.IBM Configuration for eBusiness (eConfig)
D.Advanced System Management Interface (ASMI)

在線(xiàn)練習(xí)
題目列表

你可能感興趣的試題

單項(xiàng)選擇題

Companycom wants to manage multiple partitions for a p5 590 server using Partition Load Manager (PLM). Some of the partitions are dedicated processors and some of them are shared processors.
What information about PLM limitations should be expressed to the customer?() 

A.All of the partitions can be managed in one group mixing dedicated and shared processors. PLM will move resources in the group as setup in the PLM profiles. 
B.PLM handles memory, dedicated and shared processor partitions. All the partitions in a group must be of the same processor type. PLM moves I/O resources between partitions based on PLM policy files. 
C.PLM handles memory, dedicated and shared processor partitions. The policy file, once loaded, is static and has no knowledge of workload on the managed partitions. PLM is supported for partitions that are running AIX 5.2 or i5OS. 
D.All of the partitions in a group must be the same type, either all dedicated processor partitions or shared processor partitions. One PLM Server can manage multiple groups of partitions. PLM does not move resources between groups.